Maintenance and Turnaround Schedule
|
|
2Q & 3Q Turnaround Schedule Update
|
|
4/28/2009
|
|
San Antonio
|
Valero has updated its maintenance turnaround schedule. This list includes only major projects that will have a material impact on production. While we provide general guidance on the timing and duration of the maintenance, we do not disclose specific beginning and end dates.
|
Refinery |
Unit |
BPD |
Month |
Days |
|
|
|
|
|
|
|
Paulsboro |
Coker |
27,000 |
April |
35
|
|
McKee |
#1 Crude/FCC |
60,000 |
May |
21 |
|
Delaware City |
FCC |
80,000 |
Sept. |
42 |
|
|
|
|
|
|
|
|
Three Rivers |
Plantwide |
95,000 |
Sept. |
24 |
|
|
|
|