Valero has updated its maintenance turnaround schedule. This list includes only major projects that will have a material impact on production. While we provide general guidance on the timing and duration of the maintenance, we do not disclose specific beginning and end dates.
|
Refinery |
Unit |
BPD |
Month |
Days |
|
|
|
|
|
|
|
Wilmington |
FCC/Alky* |
56,000 |
Nov. |
39 |
|
Delaware City |
FCC/Alky* |
81,000 |
Nov. |
52 |
|
Port Arthur |
FCC/Alky |
79,000 |
Jan. |
44 |
|
St. Charles |
Crude/Coker* |
190,000 |
Jan. |
36 |
|
Corpus Christi |
E. Plant HCU |
15,000 |
Jan. |
18 |
|
Corpus Christi |
W. Plant HCU |
36,000 |
Feb. |
18 |
|
Port Arthur |
Hydrocracker |
45,000 |
March |
38 |
|
Memphis |
Crude/FCC/Alky |
105,000 |
March |
45 |
|
|
|
|
|
|
|
|
* Plantwide outage