Valero has updated its maintenance turnaround schedule. This list includes only major projects that will have a material impact on production and is subject to change. While we provide general guidance on the timing and duration of the maintenance, we do not disclose specific beginning and end dates.
| Refinery |
Unit |
BPD |
Month |
Days |
| Port Arthur |
FCC/Alky |
79,000 |
Jan. |
44 |
| Corpus Christi |
E. Plant HCU |
15,000 |
Jan. |
18 |
| St. Charles |
Crude/Coker* |
190,000 |
Feb. |
30 |
| Corpus Christi |
W. Plant HCU |
36,000 |
March |
18 |
| Port Arthur |
Hydrocracker |
45,000 |
March |
38 |
| Memphis |
Crude/FCC/Alky |
105,000 |
March |
45 |
* Plantwide outage