1Q & 2Q Turnaround Schedule Update 
 
1/27/2010 
San Antonio, TX 

Valero has updated its maintenance turnaround schedule.  This list includes only major projects that will have a material impact on production and is subject to change.  While we provide general guidance on the timing and duration of the maintenance, we do not disclose specific beginning and end dates.

 
 Refinery Unit

BPD

Month

Days

 Port Arthur FCC/Alky  79,000  Jan. 44
 Corpus Christi E. Plant HCU  15,000  Jan. 18
 St. Charles Crude/Coker*  190,000  Feb. 30
 Corpus Christi W. Plant HCU  36,000  March 18
 Port Arthur Hydrocracker  45,000  March 38
 Memphis Crude/FCC/Alky  105,000  March 45


* Plantwide outage