4Q & 1Q Turnaround Schedule 
 
10/30/2012 
San Antonio, Texas 

Valero has updated its maintenance turnaround schedule.  This list includes only major projects that will have a material impact on production, and it is subject to change.  While we provide general guidance on the start and duration of the maintenance, we do not disclose specific beginning and end dates.

 

Refinery

Unit

Month

Approx. duration

Houston

Pembroke

Corpus Christi

Texas City

McKee

 

FCC

Crude

FCC

FCC

Crude

 

Sep

Oct

Jan

Jan

March

 

8 weeks

8 weeks

6 weeks

8 weeks

4 weeks

 