Valero 4Q & 1Q Turnaround Schedule 
 
10/29/2013 
San Antonio, Texas 

Valero has updated its maintenance turnaround schedule.  This list includes only major projects that will have a material impact on production, and it is subject to change.  While we provide general guidance on the start and duration of the maintenance, we do not disclose specific beginning and end dates.

  

Refinery

Unit

Month

Approx. duration

Three Rivers

FCC

 

Oct

 

6 weeks

 

Benicia

 

Coker

 

Feb

 

7 weeks

 

Corpus Christi

 

Crude/HCU

 

March

 

3 weeks

 

Memphis

 

FCC

 

March

 

8 weeks

 